Norway Pauses New Data Center Grid Reservations Until Licensing Scheme Is in Place
Norway's grid operator Statnett has paused reservations of power connections for new data centers until a government licensing scheme is in place, expected by Aug. 1, 2027. Existing connections are not affected. Energy Minister Terje Aasland said Statnett had received connection applications for 26,000 megawatts this year, more than the country's current capacity, with data centers making up 75% of requests.